| It took about 4 yards to pour the pond wall footing. It took 5 of us with two wheel barrows to do the pour smoothly. When the truck arrives, you are generally given 10 minutes for every yard of concrete that you are pouring. If you take more time than that, they charge you extra. A complicating factor was that the chute of the truck didn't reach 1/3 of the footing, so two wheel barrows came in handy. The footing is 8" thick and varies between 16" and 32" wide. Of course, it is full of rebar. | ||
| ||||||||||